Contractors have abandoned more than 50 major school upgrade projects in the Eastern Cape after government departments failed to pay them on time.
Many of the schools have been stripped of valuable materials and vandalised after they were abandoned, GroundUp reported.
One example is Makhanda's Grahamstown Primary School. The school moved into temporary prefabricated premises in February to make way for a R55m upgrade.
The revamp, originally due for completion in 2021, was to have included an administration block, a new library, an IT centre and a school hall, according to the school's principal, Leon Coetzee.
Then in June, the contractors left abruptly, telling Coetzee that the provincial Department of Public Works, the implementing agent for the project, had not paid them. This came as a complete surprise to the school, as the department had not informed them that funds were not available to pay the contractors.
"Much later, after the contractor left, the [provincial education] department came and told us that the project had been stopped until further notice," said Coetzee.
According to the provincial public works media spokesperson, Mlimandlela Ndamase, the provincial education department "over-committed for the financial year. Hence, the delays in the execution of projects and payments to contractors."
Without any security around the abandoned building site, it was quickly stripped of all valuable materials and vandalised. The windows were shattered, ceilings stripped, electrical wiring ripped, and walls smashed.
Provincial education department spokesperson Mali Mtima said that the department held no responsibility for the vandalism of the school because it is "the contractor who is responsible for their site's security".
The contractors did not respond to requests for comment.
After three months of pressure by the school, the Department of Public Works sent security personnel to guard the building site.
With the project on hold until further notice, the school governing board is concerned about the school's future. The prefabricated premises were supposed to be temporary and are already showing signs of degradation.
Coetzee said that the "floors are busy giving" and there are leakages in some of the classrooms.
Failure to pay contractors
The current crisis is not due to a lack of funds, but due to a breakdown in implementing agents paying contractors, according to Mtima.
He said that some implementing agents take on more contractors than they can afford, which leads to non-payment as they have to go through the education department to get more funding.
Another reason for non-payment, is when implementing agents submit their claims for funds late, said Mtima.
He confirmed that "about 52 major projects were affected" in the province.
Mtima said that R260m was paid to implementing agents in September to get contractors back on site, following a "cash injection from the national department".
In October 2018, the Eastern Cape branch of Equal Education released a report titled Implementing agents: The Middlemen in charge in charge of building schools, which describes the effects of failures by implementing agents on learners and teachers in the province.
Implementing agents are in charge of "managerial and project implementation" for the provincial Department of Education, says Equal Education researcher Marc Jacobs.
"They are usually state-owned enterprises, public entities or non-profit organisations" which often directly oversee the building and repair of school infrastructure, he said.
"Implementing agents typically receive 4.5% to 10% of the cost of a school infrastructure project as management fees, regardless of their performance," said Jacobs.
In the Eastern Cape, the provincial and national education departments and treasuries have failed to adequately monitor the delivery of school infrastructure. This is because they are "understaffed and do not have sufficient programme managers" to oversee the agents, according to Jacobs.
This lack of accountability leads to wasteful expenditure, and mismanagement of infrastructure sites, like that of Grahamstown Primary, he added.
Get a daily dose of New Orleans Sun news through our daily email, its complimentary and keeps you fully up to date with world and business news as well.
Publish news of your business, community or sports group, personnel appointments, major event and more by submitting a news release to New Orleans Sun.
More InformationSYDNEY, NSW, Australia - Stocks in Asia were mixed on Wednesday.Japan's Nikkei 225 eked out a small gain despite concerns ...
New Delhi [India], January 27 (ANI/Big News Network): India will reclaim the status of the world's fastest-growing economy, and will ...
NEW YORK, New York - U.S. stocks were out of favour on Tuesday with the main indices drifting lower.At the ...
NEW DELHI, India - After clashes between protestors and police in several parts of Delhi, farmers on Tuesday, the Samyukta ...
SYDNEY, NSW, Australia - Stocks in Asia lost ground on Tuesday.The Australian market missed the damage as markets were closed ...
WASHINGTON, DC, January 26 (ANI) - The U.S. Senate has confirmed Janet Yellen to be the next Secretary of the ...
On Friday, January 22, 2021, the Treaty on the Prohibition of Nuclear Weapons (TPNW) became international law for the 122 ...
Since September, the devastation wrought by the COVID-19 pandemic has deepened, infecting close to 100 million people, costing more than ...
The Russian vessel tapped to finish the controversial Nord Stream 2 gas pipeline has begun work in Danish waters just ...
President Joe Biden has issued an executive order that overturns a ban on transgender people serving in the U.S. military.In ...
NEW DELHI, India - India and China have agreed to push for an early disengagement of the frontline troops in ...
PanARMENIAN.Net - There is some evidence that a new coronavirus variant first identified in southeast England carries a higher risk ...